This roof was part of a staged contract to replace all flat roof areas on this site.
The first stage for the Hangleton Way Campus required extensive scaffolding to access the large roof area which needed to be erected during the school’s summer holiday. Due to some of the works taking place in term time, Health & Safety was paramount to protect the wellbeing of the staff and children during school hours.
The roof to the gym was in bad shape and required a full strip up of the existing system and replacing with a new Garland warm roof system as part of the second stage. These works were conducted during the school’s summer holiday.
As a trusted Garland installer for Brighton & Hove City Council, Invictus Roofing was contracted with removing the failing roof covering then supplying and fitting a new Garland felt system in accordance with the strict specifications laid out by the manufacturer. We also increased the insulation efficiency throughout the roof. New cladding and rainwater goods were also installed meaning that the water drainage needs are met to prevent future issues.
System Details
- StressPly Self-Adhesive Metal Lined VCL
- Garland TorchFlex Ultravent Underlay and Garland StressPly cap sheet in Red to area
- Garland TorchFlex Base Sheet to detail
- Works completed within 8 weeks
-
-