After the central wing of this school building suffered extensive storm damage in early 2017 Invictus Roofing was asked to replace the roof covering at short notice. As a trusted supplier for Brighton & Hove City Council, Invictus Roofing was contracted with stripping the failing roof covering and installing a new Garland 30-year felt system in accordance with the strict specifications laid out by the manufacturer, as well as increase the insulation efficiency throughout.
This project was to be started during term time, therefore the works had to be conducted under diligent Health & Safety precautions to protect the children during school hours.
System Details
- 30-year Garland build up felt
- Stressply Self-Adhesive Metal Lined VCL
- Tapered Insulation Scheme
- Garland TorchFlex Ultravent Underlay to area
- Garland TorchFlex Base Sheet to details
- Garland StressPly cap sheet in Red
- All torch applied
- Works completed within 4 weeks